Pile driving work method statement
Pile driving work method statement
I.
Material and Characteristic
1. Pile
- (PC)-Pile
type
- Concrete
strength fc28= ...... MPa (Cube’s Strength)
- Cured
age of pile at lease 7days
- Section
.... cm x ...cm
- Length ...m (Can be change in the reality of work)
- Allowable
Bearing Capacity: ......KN to .....KN
- Security
Factor bearing capacity: .....
Note: PC-Pile specification & Classification can see
on the Index I.
2. Machinery
- Hydraulic
Static Pile Driver (Robot machine)
- Diesel
Hammer (K25) machine
- Hydraulic
Hammer machine
- Drop
Hammer machine (Van Chan With 5ton Hammer)
- Other
Note: Each Machinery Specification & Classification can
see on the Index II
3. Measure tool
- Meter
- Spirit
level
- Total
station
- Other
II.
Picture
I.
Pile Driving Procedure
1.
Land preparation
2.
Pile specification
and property checking ( Any cracked on the pile is not acceptable)
3.
Pile driving
Machine installation
4.
Setting out
piling point by using total station machine
5.
Install pile on
the setting out piling point as shown in the picture No. 6.
6.
Check on the pile
vertical direction by using method as shown in picture No.7 and No.8.
7. Start the pile driving by strictly control on vertical
direction and it bearing capacity.